Nine Maryland hazard mitigation plans expire in 2028 with no update in FEMA's records. Every plan's deadline, start-by date and funding window.
Last updated
Nine of Maryland's local hazard mitigation plans expire in 2028, and FEMA's records show no update under way for any of them. They cover 38 counties, cities and towns, home to about 2.1 million people by the population figures in FEMA's plan records, from Baltimore City and Prince George's County to Dorchester and Somerset on the Eastern Shore. FEMA's 2025 Local Mitigation Planning Handbook tells communities to allow at least 18 months from kickoff to approval and to pursue funding no later than the plan's third year.
For most of those nine, the funding window has closed and the start date is months away. Four have already passed it.
If your Maryland plan expires in 2028, the update should be funded now and started by mid-2027 at the latest. The calendar below lists every Maryland plan expiring through 2028, with its start-by and funding dates, from FEMA's records on November 2, 2026.
We track these dates because we built the tool that shows them. CF Labs, Council Fire's software studio, turned FEMA's daily plan records into a public hazard mitigation plan tracker. Council Fire, a certified B Corp since 2010, was an implementation and stakeholder engagement partner for Phase I of the Annapolis Maritime Resilience Initiative, which included 18 months of community engagement on its own. Schedules slip at the public involvement stage more than anywhere else.
Because federal mitigation money follows it. Under 44 CFR 201.6, a local government needs a FEMA-approved hazard mitigation plan to receive FEMA mitigation project grants, and the plan has to be updated and resubmitted every five years. When a plan lapses, so does the eligibility, until FEMA approves the update.
That eligibility is worth real money now:
The return on that money is well documented: the National Institute of Building Sciences found that federal mitigation grants save $6 in future disaster costs for every $1 spent. An expired plan doesn't stop a county from building resilience, but it takes FEMA's share off the table.
Sixteen Maryland plans expire in 2027 or 2028, and one has already lapsed. Plans are county plans unless noted; the number after each is how many jurisdictions it covers. "Start by" is 18 months before expiration, FEMA's minimum timeline from kickoff to approval. "Funding by" is the end of the plan's third year, 24 months before expiration, when FEMA's handbook says the update should be scoped and its funding pursued.
Plan | Expires | Start by | Funding by | Update on record? |
|---|---|---|---|---|
Baltimore Co. (1) | Jan 17, 2027 | Jul 2025 | Jan 2025 | In progress |
Wicomico (9) | Apr 18, 2027 | Oct 2025 | Apr 2025 | In progress |
Frederick (13) | May 18, 2027 | Nov 2025 | May 2025 | In progress |
Talbot (6) | Jul 31, 2027 | Jan 2026 | Jul 2025 | In progress |
Harford (4) | Aug 4, 2027 | Feb 2026 | Aug 2025 | In progress |
Cecil (9) | Oct 16, 2027 | Apr 2026 | Oct 2025 | In progress |
Dorchester (10) | Jan 16, 2028 | Jul 2026 | Jan 2026 | None, start date passed |
St. Mary’s (2) | Mar 12, 2028 | Sep 2026 | Mar 2026 | None, start date passed |
Somerset (3) | Mar 13, 2028 | Sep 2026 | Mar 2026 | None, start date passed |
Mar 19, 2028 | Sep 2026 | Mar 2026 | In progress | |
Carroll (8) | Apr 17, 2028 | Oct 2026 | Apr 2026 | None, start date passed |
Annapolis (city) (1) | Jul 9, 2028 | Jan 2027 | Jul 2026 | None |
Prince George’s (2) | Sep 25, 2028 | Mar 2027 | Sep 2026 | None |
Howard (1) | Nov 5, 2028 | May 2027 | Nov 2026 | None |
Baltimore City (1) | Nov 29, 2028 | May 2027 | Nov 2026 | None |
Washington (10) | Dec 4, 2028 | Jun 2027 | Dec 2026 | None |
Worcester County's plan, which also covers Berlin, Pocomoke City and Snow Hill, expired October 5, 2025, and its update is in progress. Ocean City has its own plan.
Who this is for: county and municipal emergency managers, planners and the officials who sign grant applications. Each plan name opens its page on our Maryland tracker, which refreshes from FEMA's data daily. Nationally, the same records show 560 plans covering 4,681 jurisdictions expiring within a year, on our national tracker.
Dorchester, St. Mary's, Somerset and Carroll counties' plans expire between January and April 2028. Counting back FEMA's 18 months put their start dates between July and October 2026, and FEMA's records showed none of them in progress on November 2.
That doesn't prove nothing is happening: FEMA's "in progress" flag depends on what the state reports, and a county may be hiring help now. It does mean the margin is gone.
A late start can still finish in time if the steps overlap instead of running in sequence:
Who this is for: emergency managers in those four counties, and in any jurisdiction whose plan expires within 18 months without an update under way.
All six Maryland plans that expire in 2027 show an update in progress in FEMA's records. Frederick County held a virtual kickoff on February 10, 2026 and expects its updated plan in 2027, according to county minutes. Worcester County is the cautionary case: its plan lapsed in October 2025, and the update held public meetings in August and September 2026.
Two parts of an update are easy to underestimate, and both decide whether a plan pays off:
Who this is for: planning teams in Baltimore, Wicomico, Frederick, Talbot, Harford, Cecil and Worcester counties, and Ocean City.
Counted back from the expiration date, FEMA's guidance implies a schedule like this one:
Months before expiration | Step | FEMA's guidance |
|---|---|---|
36 to 24 | Scope the update, confirm participating jurisdictions, pursue funding | Pursue funding no later than the plan's third year; securing it can take up to 12 months |
24 to 18 | Hire a consultant if needed; sign participation agreements | Follow procurement rules; agree participation up front |
18 to 12 | Kick off; update the risk and capability assessments | At least 18 months from initiation through approval |
12 to 8 | Public involvement; revise the mitigation strategy and actions | Public comment during drafting and before approval |
8 to 6 | Draft the plan; public comment; submit to the state | |
6 to 0 | State and FEMA review; local adoption |
On that schedule, Annapolis, Prince George's, Howard, Baltimore City and Washington County are at the 20-to-25-month mark now: the funding window is closing or has closed, and kickoff should come by mid-2027. Howard County's current plan runs to November 5, 2028. Baltimore City's hazard mitigation plan is part of its Disaster Preparedness and Planning Project, which pairs it with climate adaptation.
Who this is for: jurisdictions with plans expiring in 2028 and 2029, which are in the scoping and funding years now.
FEMA's mitigation programs pay for planning as well as projects, through the state. Maryland adds sources of its own, several with dates this winter:
Our Maryland resilience funding hub lists 28 programs with their status and deadlines, re-checked against the agencies' own pages each month. Before applying, our free funding readiness scorecard flags the hard stops, including an expired plan. For the plan itself, our guide to writing an RFP for a hazard mitigation plan update covers scope, budget and evaluation.
The dates come from FEMA's Hazard Mitigation Plan Statuses dataset (OpenFEMA, version 1), retrieved November 2, 2026. We group jurisdictions by the plan they share, take each plan's expiration date from FEMA's records, and count back 18 months for "start by" and 24 months for "funding by," following FEMA's handbook. "Update in progress" means FEMA lists a newer plan record for the jurisdiction as in progress; it depends on what the state reports, so a county can be further along than the record shows. Population figures are FEMA's.
This product uses the Federal Emergency Management Agency's OpenFEMA API, but is not endorsed by FEMA. The Federal Government or FEMA cannot vouch for the data or analyses derived from these data after the data have been retrieved from the Agency's website(s).
Baltimore County's plan expires January 17, 2027, and FEMA's records show its update in progress. Five more Maryland plans expire later in 2027 and ten in 2028, by FEMA's data on November 2, 2026. Worcester County's plan already expired, on October 5, 2025. Our Maryland tracker shows every jurisdiction's current date.
FEMA's 2025 Local Mitigation Planning Handbook says to allow at least 18 months from kickoff to FEMA approval, including at least six months for state and FEMA review. It also says to scope the update and pursue funding no later than the plan's third year, because securing funding can take up to 12 months.
The jurisdiction loses eligibility for FEMA mitigation project grants until FEMA approves an updated plan, under 44 CFR 201.6. Worcester County's plan expired October 5, 2025, so it and three of its towns can't receive those grants until FEMA approves the update now under way. Planning work can continue throughout.
Every five years. A FEMA-approved local hazard mitigation plan expires five years after approval, and the update must repeat the whole planning process, including public involvement, before FEMA approves it again. FEMA's handbook lets teams validate parts of the old plan with fewer major changes rather than rewrite everything.
The Maryland Department of Emergency Management reviews local plans before they go to FEMA, which approves them. Each participating jurisdiction must also adopt the plan. FEMA's handbook says to budget at least six months for state and FEMA review, so submit well before the current plan expires.
Yes. FEMA's mitigation programs fund planning as well as projects, applied for through the state, and Maryland agencies fund related flood planning, such as the Department of Natural Resources' Community Flood Planning grants. Our resilience funding hub lists current programs and deadlines.
Our free hazard mitigation plan tracker shows any U.S. jurisdiction's plan status, expiration date, start-by and funding-by dates from FEMA's data, refreshed daily. Maryland's 24 counties and Baltimore City each have their own page, and you can have the timeline emailed to you.
Tell us your plan's expiration date and where the update stands. We'll map the schedule back from that date, show which programs your projects could compete for and when, and say what belongs in the scope. Talk to us on our contact page and choose Climate resilience.
George Chmael II is Council Fire's Founder & CEO. He has led the firm since its founding and through its B Corp certification in 2010. Council Fire's climate resilience practice works with cities, counties, ports and authorities on planning, funding and delivery, and CF Labs builds the software that holds that work together.