Dorchester County hazard mitigation plan

Dorchester County’s plan expires January 16, 2028: 444 days from today. FEMA says to allow at least 18 months from kickoff to approval, so the update should already be under way.

Status
Start nowUpdate should be under way
Expires
Jan 2028444 days from today
Start the update by
NowScope and funding by January 16, 2026
Jurisdictions on file
102 covered by a current plan

FEMA data retrieved October 29, 2026, read again daily · How we read it

The update timeline

Plan
Dorchester County Hazard Mitigation Plan
FEMA approval
January 17, 2023
Expires
January 16, 2028
Line up scope and funding by
January 16, 2026 (passed)
Start the update by
July 16, 2026 (passed)
Status
Update should be under way

Get these dates by email

Dorchester County’s status, the update dates and the guides for planning it, in one email.

One email now, and nothing else unless you tick the box.

Every jurisdiction in Dorchester County

The county and the towns inside it, as FEMA lists them. A town shares its county plan’s dates only if it took part and adopted the plan.

Jurisdictions in Dorchester County and their hazard mitigation plans
JurisdictionStatusExpiresPlan
Dorchester CountyCountyUpdate should be under wayJanuary 16, 2028444 daysDorchester County Hazard Mitigation Plan
BrookviewTownApprovable pending adoptionJanuary 16, 2028444 daysDorchester County Hazard Mitigation Plan
CambridgeCityUpdate should be under wayJanuary 16, 2028444 daysDorchester County Hazard Mitigation Plan
Church CreekTownApprovable pending adoptionJanuary 16, 2028444 daysDorchester County Hazard Mitigation Plan
East New MarketTownApprovable pending adoptionJanuary 16, 2028444 daysDorchester County Hazard Mitigation Plan
EldoradoTownApprovable pending adoptionJanuary 16, 2028444 daysDorchester County Hazard Mitigation Plan
GalestownTownApprovable pending adoptionJanuary 16, 2028444 daysDorchester County Hazard Mitigation Plan
HurlockTownApprovable pending adoptionJanuary 16, 2028444 daysDorchester County Hazard Mitigation Plan
SecretaryTownApprovable pending adoptionJanuary 16, 2028444 daysDorchester County Hazard Mitigation Plan
ViennaTownApprovable pending adoptionJanuary 16, 2028444 daysDorchester County Hazard Mitigation Plan

The risks the plan has to address

FEMA expects hazards to cost Dorchester County $15.7M in an average year, led by coastal flooding at $5.8M. The county’s climate risk profile ranks every hazard and lists FEMA’s mitigation grants there.

Dorchester County climate risk profile

How we read FEMA’s data

Every status here comes from FEMA’s Hazard Mitigation Plan Statuses dataset (OpenFEMA API, v1 endpoint), retrieved October 29, 2026 at 7:12 PM EDT and read again once a day.

FEMA lists one record for each jurisdiction in each plan. We group the records by jurisdiction: one is current while any plan it adopted has an approval that hasn’t expired. “Approvable pending adoption” means FEMA has approved the plan and is waiting on the jurisdiction to adopt it. Plan updates run on a five-year cycle (44 CFR 201.6), and the update dates follow FEMA’s 2025 Local Mitigation Planning Handbook: allow at least 18 months from kickoff to approval, and line up the scope and funding by the plan’s third year. We leave out records FEMA labels as tests.

This is a planning aid, not an eligibility ruling: confirm grant eligibility with your state hazard mitigation officer or FEMA.

This product uses the Federal Emergency Management Agency’s OpenFEMA API, but is not endorsed by FEMA. The Federal Government or FEMA cannot vouch for the data or analyses derived from these data after the data have been retrieved from the Agency’s website(s).

Frequently Asked Questions

It runs to January 16, 2028, according to FEMA’s plan records as of October 29, 2026. The plan is the Dorchester County Hazard Mitigation Plan, approved by FEMA on January 17, 2023. Local plans have to be updated and approved again every five years.
By July 16, 2026, with the scope and funding lined up by January 16, 2026. FEMA’s 2025 Local Mitigation Planning Handbook says to allow at least 18 months from kickoff to approval, six of them for state and FEMA review, and to line up the update by the plan’s third year.
FEMA lists 1 other jurisdiction with a current approval under the same plan: Cambridge. Each shares the plan’s expiration date, and each has to adopt the update too.
Dorchester County publishes it at https://www.dorchestermd.gov/DocumentCenter/View/168. FEMA’s records show its approval and expiration dates; the plan itself sets out the county’s hazards and the projects it intends to fund.