19 of 22 Pennsylvania county hazard mitigation plans expiring by 2028 have an update moving. Three don't. Every county's deadline and PEMA's schedule.
Last updated
Pennsylvania counties start their hazard mitigation plan updates early, and FEMA's records show it. Of the 22 county plans that have expired or will expire by the end of 2028, 19 had an update in progress, in FEMA review or approved and awaiting adoption on November 2, 2026, according to FEMA's plan records. Three did not: Franklin, Elk and Berks counties, whose plans expire in October and November 2028 and cover 105 jurisdictions and about 600,000 people.
The Pennsylvania Emergency Management Agency's 2025 planning guide runs on a longer clock than FEMA's minimum: apply for FEMA funding 36 months before a plan expires, because the award "normally takes 12 months," and hold the public kickoff meeting 24 months before. For those three counties, the kickoff date falls this fall.
If your county plan expires in late 2028, the update should be funded and the planning team assembled now. The calendar below lists every Pennsylvania county plan expiring through 2028, with PEMA's funding and kickoff dates and how far each update has got.
We track these dates because we built the tool that shows them. CF Labs, Council Fire's software studio, turned FEMA's daily plan records into a public hazard mitigation plan tracker that covers every state. Council Fire, a certified B Corp since 2010, was an implementation and stakeholder engagement partner for Phase I of the Annapolis Maritime Resilience Initiative, which included 18 months of community engagement on its own, and we published the same calendar for Maryland, where nine plans are further behind.
Because federal mitigation money follows it. Under 44 CFR 201.6, a local government needs a FEMA-approved hazard mitigation plan to receive FEMA mitigation project grants, and plans must be updated and resubmitted every five years.
Pennsylvania adds a twist that raises the stakes. FEMA requires plans to be adopted by the level of government with land use authority, which in Pennsylvania means its 2,560 municipalities, so counties write multi-jurisdictional plans and municipalities adopt them, PEMA's guide explains. Since 2024, FEMA has also required any organization seeking mitigation funding to participate in and adopt its county's plan, which the guide says reaches the state's 1,860 municipal authorities and 500-plus school districts. A water authority that skips the county update can't apply later.
That eligibility is worth real money now:
The return on that money is well documented: the National Institute of Building Sciences found that federal mitigation grants save $6 in future disaster costs for every $1 spent.
Twenty-one county plans expire by the end of 2028, and one has already lapsed. The number after each county is how many jurisdictions its plan covers. "Apply for funding by" is 36 months before expiration and "Kick off by" is 24 months before, following PEMA's suggested schedule. "Update on record" is the furthest stage FEMA's records show for the county's next plan.
Plan | Expires | Apply for funding by | Kick off by | Update on record? |
|---|---|---|---|---|
Adams (34) | Dec 6, 2025 (expired) | Dec 2022 | Dec 2023 | In FEMA review |
Beaver (48) | Nov 7, 2026 | Nov 2023 | Nov 2024 | In FEMA review |
Butler (44) | Nov 22, 2026 | Nov 2023 | Nov 2024 | In progress |
Carbon (24) | Jan 23, 2027 | Jan 2024 | Jan 2025 | In progress |
Washington (67) | Mar 6, 2027 | Mar 2024 | Mar 2025 | In progress |
Tioga (42) | May 8, 2027 | May 2024 | May 2025 | In progress |
Cameron (7) | Jul 10, 2027 | Jul 2024 | Jul 2025 | In progress |
Clearfield (40) | Jul 12, 2027 | Jul 2024 | Jul 2025 | In progress |
Cambria (63) | Aug 1, 2027 | Aug 2024 | Aug 2025 | In progress |
Pike (13) | Sep 27, 2027 | Sep 2024 | Sep 2025 | In progress |
Northumberland (15) | Oct 9, 2027 | Oct 2024 | Oct 2025 | In progress |
Fayette (38) | Jan 30, 2028 | Jan 2025 | Jan 2026 | Approved, pending adoption |
Delaware (27) | Feb 26, 2028 | Feb 2025 | Feb 2026 | In progress |
Mercer (48) | Mar 19, 2028 | Mar 2025 | Mar 2026 | In progress |
Columbia (34) | Apr 2, 2028 | Apr 2025 | Apr 2026 | In progress |
Bedford (37) | Apr 3, 2028 | Apr 2025 | Apr 2026 | In progress |
Clarion (43) | Apr 4, 2028 | Apr 2025 | Apr 2026 | In progress |
Erie (38) | Apr 9, 2028 | Apr 2025 | Apr 2026 | In progress |
Montgomery (62) | Apr 11, 2028 | Apr 2025 | Apr 2026 | In progress |
Franklin (21) | Oct 23, 2028 | Oct 2025 | Oct 2026 | None on record |
Elk (12) | Oct 31, 2028 | Oct 2025 | Oct 2026 | None on record |
Berks (72) | Nov 5, 2028 | Nov 2025 | Nov 2026 | None on record |
Who this is for: county emergency management coordinators and planners, and the municipal managers, authority directors and school district officials who will have to adopt the next plan. To look up a single municipality, open our tracker and choose Pennsylvania.
Franklin, Elk and Berks counties' plans expire on October 23, October 31 and November 5, 2028. PEMA's guide would have had them apply for FEMA funding in the fall of 2025 and hold their kickoff meetings this fall, and FEMA's records show no update for any of them. That doesn't prove nothing is happening: FEMA's records depend on what the state reports, and a county may be scoping the work now. It does mean the easy schedule is gone.
Two years is still enough if the steps start now and overlap:
Who this is for: emergency management staff in Franklin, Elk and Berks counties, and any county whose plan expires within three years without an update under way.
They show how a gap opens even when a county is working on the update. Beaver County's plan expires November 7, 2026, and its update is in FEMA review rather than approved, so its 48 jurisdictions may spend weeks or months between plans. Adams County's plan lapsed on December 6, 2025, and its update was still in FEMA review on November 2, 2026. Until FEMA approves it and the municipalities adopt it, Adams County's 34 jurisdictions can't receive FEMA mitigation project grants.
The fix is the one PEMA's schedule builds in: submit early enough that state review, FEMA's review and every adoption vote fit before the old plan runs out. Our guide to hazard mitigation plan implementation covers what to do with the plan's actions once it's approved.
Who this is for: counties with plans expiring in 2027, all eight of which have updates in progress, and the municipalities waiting to adopt them.
PEMA's suggested schedule, counted back from expiration, runs longer than FEMA's 18-month minimum:
Months before expiration | Step in PEMA's schedule |
|---|---|
36 | Apply for Hazard Mitigation Assistance through PEMA; the award normally takes 12 months |
More than 24 | Build the planning team, invite participants and stakeholders, get FEMA's review of the current plan |
24 | Stakeholder outreach plan; public kickoff meeting with every municipality |
24 to 18 | Review existing plans, update the community profile, profile hazards |
18 | Vulnerability and risk assessment; public risk assessment review meeting |
18 to 6 | Capability assessment and mitigation strategy |
6 | Public draft review meeting; at least 30 days of public comment |
6 to 3 | Final plan |
At least 3 | Submit to PEMA, which reviews it and sends it to FEMA for at least 45 days of review |
Who this is for: counties with plans expiring in 2029 and 2030, which are in the funding and team-building years now.
FEMA's mitigation programs pay for planning as well as projects, applied for through PEMA. Pennsylvania adds a source of its own: the Commonwealth Financing Authority's Flood Mitigation Program, funded under Act 13 of 2012, grants up to $500,000 for flood mitigation projects of $50,000 or more, with a 15% match, according to its guidelines. Its last application window closed May 31, 2026.
Before applying for anything, our free funding readiness scorecard flags the hard stops, including an expired plan, and our guides cover writing an RFP for a hazard mitigation plan update and applying for a FEMA mitigation grant.
The dates come from FEMA's Hazard Mitigation Plan Statuses dataset (OpenFEMA, version 1), retrieved November 2, 2026. We group jurisdictions by the county plan they share, take each plan's expiration date from FEMA's records, and count back 36 and 24 months following PEMA's 2025 guide. "Update on record" is the furthest stage FEMA lists for each county's next plan (in progress, in review, or approved and pending adoption); it depends on what the state reports, so a county can be further along than the record shows.
A few municipalities sit outside their county's plan: one Bucks County borough remains on the county's earlier plan, which expired October 3, 2026. Population figures are FEMA's.
This product uses the Federal Emergency Management Agency's OpenFEMA API, but is not endorsed by FEMA. The Federal Government or FEMA cannot vouch for the data or analyses derived from these data after the data have been retrieved from the Agency's website(s).
Counties do. FEMA requires plans to be adopted by the government with land use authority, which in Pennsylvania is the municipality, so each county prepares a multi-jurisdictional plan that its municipalities participate in and adopt. PEMA reviews county plans before FEMA approves them, under its 2025 standard operating guide.
PEMA's 2025 guide suggests applying for FEMA funding 36 months before the plan expires, since the award usually takes 12 months, building the planning team more than 24 months out and holding the public kickoff meeting 24 months before expiration. FEMA's own handbook sets a floor of 18 months from kickoff to approval.
Franklin, Elk and Berks counties, as of FEMA's records on November 2, 2026. Their plans expire October 23, October 31 and November 5, 2028, and together cover 105 jurisdictions and about 600,000 people. FEMA's records depend on state reporting, so check with the county before assuming nothing has started.
Yes, if they want FEMA mitigation funding. PEMA's guide says that since 2024 FEMA has required any organization seeking hazard mitigation funding to participate in and adopt the county plan. That includes Pennsylvania's 1,860 municipal authorities and more than 500 school districts, as well as municipalities.
Its municipalities lose eligibility for FEMA mitigation project grants until FEMA approves the update and they adopt it, under 44 CFR 201.6. Adams County's plan lapsed on December 6, 2025, and its update was still in FEMA review in November 2026. Planning work and locally funded projects can continue.
Yes. FEMA's Hazard Mitigation Assistance programs fund planning as well as projects, applied for through PEMA's E-grants system. Pennsylvania's Flood Mitigation Program, run by the Commonwealth Financing Authority, funds flood mitigation projects of up to $500,000 with a 15% match.
Our free hazard mitigation plan tracker shows any U.S. jurisdiction's plan status, expiration date and update dates from FEMA's data, refreshed daily. Choose Pennsylvania in the lookup to see each county and municipality, with its plan's FEMA approval and expiration dates, and email yourself the timeline for any of them.
Tell us your county plan's expiration date and where the update stands. We'll map PEMA's schedule back from that date, show which programs your projects could compete for and when, and say what belongs in the scope. Talk to us on our contact page and choose Climate resilience.
George Chmael II is Council Fire's Founder & CEO. He has led the firm since its founding and through its B Corp certification in 2010. Council Fire's climate resilience practice works with cities, counties, ports and authorities on planning, funding and delivery, and CF Labs builds the software that holds that work together.